How Much Cement Required For Plastering?

How Much Cement Required For Plastering
no of cement bags required per square metre for plastering – 1) plastering thickness 12mm & cement sand ratio 1:4 :- For a Sample calculation, I will assume a 12mm (0.012m) thick plaster and a mix ratio of 1:4 for plastering of 1 square metre brick wall ● Step-1: we know given area of brick wall = 1 sq m ● Step-2: Volume of brick wall plaster = Area X Thickness = 1 X 0.012 = 0.012 m3 Since wet volume is always less than the dry volume.

  • For converting wet volume to dry volume of mortar we will multiply 1.33 into wet volume.
  • The dry volume of mortar required for brick wall plastering = 1.33 X Dry volume of plaster = 1.33 X 0.012 = 0.01596 m3.
  • Step-3: The mix ratio of mortar is 1:4, So total ratio = 1+4 = 5 in which one part is cement and 4 part is sand Cement required = 1/5 X 0.01596 = 0.003192 cu m ( cubic meter) Sand required = 4/5 X 0.01596 = 0.01277 cu m ● Step-4: To get the weights of materials required in multiply it with its density and convert cubic feet into cubic meter Cement required = 0.003192 cum X 1440 kg/cum = 4.6 Kgs Since Sand density is 1620 kg/m3 Then quantity of sand = 0.01277 ×1620 = 21Kgs.

● Ans :- 21 Kgs (0.01277 cu m) sand and 0.092 bags (4.6 Kgs) cement required per square metre for plastering in 12mm thick plaster & ratio 1:4.2) Quantity of sand and cement bags per square metre for plastering in 20mm thick plaster & mix ratio 1:4 cement required for 1 sq m plastering of brick wall :- For a Sample calculation, I will assume a 20mm (0.020) thick plaster and a mix ratio of 1:4 for plastering of 1 sq m brick wall ● Step-1: we know given area of brick wall = 1 sq m ● Step-2: Volume of brick wall plaster = Area X Thickness = 1 X 0.020 = 0.020 cu m Since wet volume is always less than the dry volume.

For converting wet volume to dry volume of mortar we will multiply 1.33 into wet volume. The dry volume of mortar required for brick wall plastering = 1.33 X Dry volume of plaster = 1.33 X 0.020 = 0.0266 cu m. ● Step-3: The mix ratio of mortar is 1:4, So total ratio = 1+4 = 5 in which one part is cement and 4 part is sand Cement required = 1/5 X 0.0266 = 0.00532 cu m ( cubic meter) Sand required = 4/5 X 0.0266 = 0.02128 cu m ● Step-4: To get the weights of materials required in multiply it with its density and convert cubic feet into cubic meter Cement required = 0.00532 cum X 1440 kg/cum = 7.7 Kgs Since Sand density = 1620 kg/m3 Then quantity of sand = 0.02128 × 1620 = 34.5 Kgs.

You might be interested:  What Is The Reason For White Cement To Be White?

● Ans :- 34.5 Kgs (0.02128 m3) sand and 0.154 bags (7.7 Kgs) cement required per square metre for plastering in 20mm thick plaster 1:4. ALSO READ :- Plaster sand near me, delivery, colour and 25kg or bulk bag Cement to sand ratio for mortar, brickwork and plastering How to calculate plastering quantity | cement sand ratio How to calculate the quantity of material for plaster Plaster cost per square foot with material in India Sand required for 1 sqm plastering:- sand requirement depend on thickness of plastering, around 21kgs to 34kgs sand required for 1 sqm plastering.

  1. Now question is how many cement bags per square metre for plastering? ● Ans.
  2. 0.092 bags cement are required per square metre for plastering in case of 12 mm thick plaster & cement sand ratio 1:4 ● Ans.0.154 bags cement required per square metre for plastering in case of 20 thick plaster & cement sand ratio 1:4.

◆You Can Follow me on Facebook and Subscribe our Youtube Channel You should also visits:- 1)what is concrete and its types and properties 2) concrete quantity calculation for staircase and its formula

How much cement do I need to plaster a wall?

no of cement bags required per square metre for plastering – 1) plastering thickness 12mm & cement sand ratio 1:4 :- For a Sample calculation, I will assume a 12mm (0.012m) thick plaster and a mix ratio of 1:4 for plastering of 1 square metre brick wall ● Step-1: we know given area of brick wall = 1 sq m ● Step-2: Volume of brick wall plaster = Area X Thickness = 1 X 0.012 = 0.012 m3 Since wet volume is always less than the dry volume.

  • For converting wet volume to dry volume of mortar we will multiply 1.33 into wet volume.
  • The dry volume of mortar required for brick wall plastering = 1.33 X Dry volume of plaster = 1.33 X 0.012 = 0.01596 m3.
  • Step-3: The mix ratio of mortar is 1:4, So total ratio = 1+4 = 5 in which one part is cement and 4 part is sand Cement required = 1/5 X 0.01596 = 0.003192 cu m ( cubic meter) Sand required = 4/5 X 0.01596 = 0.01277 cu m ● Step-4: To get the weights of materials required in multiply it with its density and convert cubic feet into cubic meter Cement required = 0.003192 cum X 1440 kg/cum = 4.6 Kgs Since Sand density is 1620 kg/m3 Then quantity of sand = 0.01277 ×1620 = 21Kgs.
You might be interested:  Which Accounting Standard Covers Accounting For Construction Contracts?

● Ans :- 21 Kgs (0.01277 cu m) sand and 0.092 bags (4.6 Kgs) cement required per square metre for plastering in 12mm thick plaster & ratio 1:4.2) Quantity of sand and cement bags per square metre for plastering in 20mm thick plaster & mix ratio 1:4 cement required for 1 sq m plastering of brick wall :- For a Sample calculation, I will assume a 20mm (0.020) thick plaster and a mix ratio of 1:4 for plastering of 1 sq m brick wall ● Step-1: we know given area of brick wall = 1 sq m ● Step-2: Volume of brick wall plaster = Area X Thickness = 1 X 0.020 = 0.020 cu m Since wet volume is always less than the dry volume.

  • For converting wet volume to dry volume of mortar we will multiply 1.33 into wet volume.
  • The dry volume of mortar required for brick wall plastering = 1.33 X Dry volume of plaster = 1.33 X 0.020 = 0.0266 cu m.
  • Step-3: The mix ratio of mortar is 1:4, So total ratio = 1+4 = 5 in which one part is cement and 4 part is sand Cement required = 1/5 X 0.0266 = 0.00532 cu m ( cubic meter) Sand required = 4/5 X 0.0266 = 0.02128 cu m ● Step-4: To get the weights of materials required in multiply it with its density and convert cubic feet into cubic meter Cement required = 0.00532 cum X 1440 kg/cum = 7.7 Kgs Since Sand density = 1620 kg/m3 Then quantity of sand = 0.02128 × 1620 = 34.5 Kgs.

● Ans :- 34.5 Kgs (0.02128 m3) sand and 0.154 bags (7.7 Kgs) cement required per square metre for plastering in 20mm thick plaster 1:4. ALSO READ :- Plaster sand near me, delivery, colour and 25kg or bulk bag Cement to sand ratio for mortar, brickwork and plastering How to calculate plastering quantity | cement sand ratio How to calculate the quantity of material for plaster Plaster cost per square foot with material in India Sand required for 1 sqm plastering:- sand requirement depend on thickness of plastering, around 21kgs to 34kgs sand required for 1 sqm plastering.

Now question is how many cement bags per square metre for plastering? ● Ans. :- 0.092 bags cement are required per square metre for plastering in case of 12 mm thick plaster & cement sand ratio 1:4 ● Ans.0.154 bags cement required per square metre for plastering in case of 20 thick plaster & cement sand ratio 1:4.

◆You Can Follow me on Facebook and Subscribe our Youtube Channel You should also visits:- 1)what is concrete and its types and properties 2) concrete quantity calculation for staircase and its formula

You might be interested:  Which Construction Company Made Burj Khalifa?

How much cement consumption in 12mm thick plaster 1 4?

Cement Consumption in Plaster- – Cement consumption in 12mm thick plaster 1:4 for 1 m 2 plastering of a brick wall is 0.092 bags (4.6 kg) cement, Ans :- 4.6 kg (0.092 bags), 46 kg (0.92 bags) & 460 kg (9.2 bags) are cement consumption and requirement in 12mm thick plaster 1:4 for 1 m 2, 10 m 2 & 100 m 2 area of brick wall respectively.

How to calculate cement sand quantity for plastering?

How to Calculate the Cement Sand Quantity for Plastering? –

  1. Density of Cement = 1440 kg/m 3,
  2. Sand Density = 1450-1500 kg/m 3,
  3. Density of Aggregate = 1450-1550 kg/m 3
  4. How many KG in 1 bag of cement = 50kg.
  5. Cement quantity in liters in 1 bag of cement = 34.7 litres.
  6. 1 Bag of cement in cubic metres = 0.0347 cubic metre.
  7. How many CFT (Cubic Feet) = 1.226 Cu.Ft.
  8. Numbers of Bags in 1 cubic metre cement = 28.8 Bags

What is the mix ratio of plastering plaster?

How many cement bags per square meter for plastering? cement bags required for 1 sq m plastering, hi guys in this post we know about how much cement is required for plastering of 1 square meter area & also know about cement required for 1 sq m in 12mm & 20mm thick plaster.

WATCH THIS VIDEO Requirement of plastering material cement and sand calculation in plaster of brick wall depends on mostly two factors such as 1) Thickness of Plaster 2) Mix Ratio (Cement:Sand) 1) thickness of cement plaster :- recommended thickness of cement plaster is 6 mm (for ceiling and concrete plastering), 12 mm (for internal wall plastering and plane surface of brickwork) & 15 mm or 20 mm (for external wall plastering and rough surface of brickwork) are used in building construction.

● 6 mm thick cement plaster are used for ceiling and concrete plastering ● 12 mm thick cement plaster are used for internal wall plastering and plane surface of brick wall ● 15 mm or 20 mm theek cement plaster used for external wall plastering and rough surface of brick wall 2) mix ratio for cement plaster : there are several types of mix ratio used for brick wall plastering, ratio of cement and sand for plastering depends on types of work and plastering types it is rough or plane surface. How many cement bags per square meter for plastering?